Create Plan of Action & Milestones

How to create and maintain a FedRAMP-compliant POA&M to track security weaknesses and remediation progress.

A Plan of Action & Milestones (POA&M) is a required security artifact that tracks known security weaknesses, remediation plans, and progress toward resolution. For systems authorized under FedRAMP, the POA&M provides transparency to Authorizing Officials (AOs), security assessors, and stakeholders by documenting:

  • Identified vulnerabilities
  • The associated control weaknesses
  • Planned remediation actions
  • Responsible parties
  • Target remediation dates
  • Risk status and severity

Update the POA&M whenever you discover, remediate, or reassess vulnerabilities.


When to create a POA&M

You must create or update a POA&M when:

  • A security control fails or is limitedly implemented
  • A vulnerability scan identifies a finding
  • A penetration test identifies exploitable weaknesses
  • A Security Assessment Report (SAR) identifies control deficiencies
  • A continuous monitoring activity detects new issues
  • A risk acceptance decision requires tracking mitigation activities

Key components of a POA&M document

A FedRAMP-compliant POA&M entry typically includes these 11 fields:

  • POA&M ID: Unique identifier for the weakness
  • Control ID: Associated NIST SP 800-53 control (for example, AC-2, SI-2)
  • Weakness Description: Summary of the security issue
  • Source of Finding: Scan, assessment, or test identifying the weakness
  • Severity: Risk rating (High / Moderate / Low)
  • Remediation Plan: Steps planned to correct the issue
  • Milestones: Intermediate remediation steps
  • Responsible Party: Team responsible for remediation
  • Scheduled Completion Date: Planned remediation deadline
  • Status: Open, In Progress, or Closed
  • Comments: Optional context or justification
How to complete POA&M requirements with the Security Advisory Services and Agency

The Security Advisory Services and Agency will work with you to create and maintain your application's POA&M. Responsibilities divide as follows:

  • Security Advisory Services and Agency:

    • Identify the security weaknesses in your application
    • Map each finding to the applicable security control
    • Determine severity and required completion date
  • Your organization:

    • Define a remediation plan for each finding
    • Assign ownership and accountability for remediation

The POA&M creation process

While the Security Advisory Services and Agency team leads the technical mapping of your POA&M, the following steps outline the standard process. Review these steps to understand how vulnerabilities become actionable remediation plans.

Identify the security weakness

Start by documenting the finding clearly and concisely. Include:

  • The affected system component
  • How the issue was identified
  • The potential security impact

Example: Container image scan identified a critical vulnerability in the OpenSSL dependency used by the application container.

Map the finding to a security control

Associate each POA&M entry with the relevant NIST SP 800-53 control.

Example mappings:

Finding TypeLikely Control
Vulnerable dependencySI-2 Flaw Remediation
Excessive privilegesAC-6 Least Privilege
Weak encryptionSC-13 Cryptographic Protection
Missing loggingAU-2 Event Logging

Determine the severity

FedRAMP severity ratings generally align with CVSS scoring or assessor risk ratings.

SeverityDescription
HighRequires immediate remediation
ModerateRequires remediation within defined timelines
LowMinor or informational issue

Define a remediation plan

Describe the actions required to eliminate the vulnerability. Include:

  • Technical remediation
  • Configuration updates
  • Dependency upgrades
  • Process improvements

Example remediation actions:

  • Update vulnerable dependency
  • Apply security patches
  • Modify IAM policies
  • Harden configuration settings

Assign responsibility

Assign each POA&M item a clearly identified owner, such as the DevOps or Application team.

Establish completion dates

FedRAMP programs often require remediation timelines based on severity. Review the Acceptance Baseline Criteria for the exact timeline.

Example POA&M Entry

POA&M Entry
POA&M IDWeakness NameWeakness DescriptionControl IDSource of FindingAffected AssetsSecurity ImpactRisk SeverityRemediation PlanMilestones with Completion DatesPlanned Completion DateResources RequiredResponsible PartyStatusComments
POAM-2026-001Vulnerable OpenSSL dependency in application containerA container image scan identified a critical OpenSSL vulnerability (CVE-2025-12345) in the application container image used in the production environment.SI-2Container Image ScanProduction application container imageExploitation of the vulnerable library could allow compromise of application confidentiality, integrity, or availability.HighUpgrade OpenSSL to the patched version, rebuild the container image, validate the fix through rescanning, and deploy the updated image through the approved release process.1. Validate vulnerability applicability - 2026-03-20; 2. Upgrade dependency - 2026-03-25; 3. Rebuild image and rescan - 2026-03-28; 4. Deploy to staging and production - 2026-04-10; 5. Verify closure - 2026-04-152026-04-15Engineering time, CI/CD pipeline support, security validationApplication Engineering TeamIn ProgressPatch included in the next approved release cycle. Security team will review scan evidence before closure.
POAM-2026-002Inactive accounts not disabled within required timeframeUser accounts that have been inactive for more than 35 days remain enabled in the identity management system.AC-2Security Control AssessmentIdentity provider and application-integrated user accountsStale accounts increase the risk of unauthorized access through dormant or unmanaged credentials.ModerateImplement automated inactivity monitoring, disable inactive accounts after the approved threshold, and document periodic account review procedures.1. Review inactive account inventory - 2026-04-05; 2. Implement automated disablement rule - 2026-04-15; 3. Disable existing stale accounts - 2026-04-20; 4. Update SOP and evidence collection process - 2026-05-012026-05-01IAM administrator support, identity platform configuration updatesIdentity & Access Management TeamOpenManual reviews are currently performed inconsistently. Automation is required for sustained compliance.
POAM-2026-003Incomplete logging of administrative actionsAdministrative actions performed through the management interface are not consistently captured in centralized audit logs.AU-2Penetration TestApplication admin portal and centralized logging pipelineMissing audit trails reduce the ability to detect, investigate, and respond to unauthorized or inappropriate administrative activity.ModerateUpdate application logging to record administrative events, forward logs to the centralized monitoring platform, and validate retention and searchability.1. Identify missing admin events - 2026-04-10; 2. Update logging instrumentation - 2026-04-25; 3. Integrate with centralized logging service - 2026-05-05; 4. Validate event capture and retention - 2026-05-202026-05-20Developer support, logging pipeline updates, validation testingPlatform EngineeringOpenExisting logs capture authentication events but not all privilege-changing or configuration actions.
POAM-2026-004Deprecated TLS cipher suites enabled for internal servicesConfiguration compliance scans identified deprecated TLS cipher suites enabled on internal service-to-service communication endpoints.SC-13Configuration Compliance ScanInternal API gateways and service endpointsWeak cryptographic settings could allow downgrade attacks or weaken protection of data in transit.HighUpdate TLS configuration baselines, disable deprecated cipher suites, redeploy affected services, and validate using configuration and network testing.1. Inventory affected services - 2026-03-18; 2. Update TLS baseline configuration - 2026-03-24; 3. Redeploy services - 2026-04-02; 4. Validate secure cipher enforcement - 2026-04-102026-04-10DevOps support, configuration management updates, validation testingDevOps TeamIn ProgressStaging remediation is complete. Production rollout is pending completion of change control review.
POAM-2026-005Privileged containers allowed by default in cluster policyKubernetes cluster configuration permits privileged containers to run without requiring documented exception approval.CM-6Configuration ReviewKubernetes admission policy and workload configurationPrivileged containers may enable container breakout or unauthorized host-level access.HighImplement admission controls to block privileged containers by default, establish an exception workflow, and retest workloads for compatibility.1. Draft admission control policy - 2026-03-30; 2. Test policy in non-production cluster - 2026-04-08; 3. Deploy policy to production - 2026-04-18; 4. Publish exception procedure - 2026-04-252026-04-25Platform security engineering, cluster admin support, workload testingPlatform Security TeamOpenA temporary review process exists, but enforcement is not yet technical or automated.
POAM-2026-006Password policy does not meet required complexity settingsThe identity provider configuration does not fully enforce password complexity and minimum length requirements expected for the environment.IA-5Security Assessment ReportEnterprise identity providerWeak password requirements increase the likelihood of credential compromise and unauthorized access.ModerateUpdate password policy settings in the identity provider, validate enforcement, and document the updated authenticator management configuration.1. Review current password settings - 2026-04-12; 2. Update identity provider policy - 2026-04-25; 3. Test policy enforcement - 2026-05-02; 4. Update supporting documentation - 2026-05-102026-05-10IAM administrator support, user communications, validation testingIdentity Management TeamOpenMFA is enabled, but password policy configuration still requires adjustment to meet baseline expectations.
POAM-2026-007Vulnerability scanning not consistently performed across environmentsMonthly vulnerability scans are not being executed consistently across staging and production environments, and tracking evidence is incomplete.RA-5Continuous Monitoring ReviewProduction and staging environmentsInconsistent scanning may delay identification of exploitable vulnerabilities and weaken continuous monitoring effectiveness.ModerateAutomate recurring vulnerability scans for all in-scope environments, centralize scan results, and track completion evidence in the security workflow.1. Confirm environment inventory - 2026-04-15; 2. Configure automated scan schedules - 2026-04-30; 3. Integrate results with tracking system - 2026-05-15; 4. Validate monthly reporting process - 2026-05-302026-05-30Security operations support, scanner licensing, reporting workflow updatesSecurity OperationsOpenCurrent scanning is manual and depends on individual team follow-through.

Best practices

To ensure your POA&M remains effective:

  • Keep entries concise and actionable. Focus on clear, specific remediation steps rather than vague descriptions.
  • Focus on risk. Address High severity findings first.
  • Track progress consistently. Update status to reflect current remediation state.
  • Align with scan results. Ensure POA&M items stay in sync with the latest vulnerability scan outputs.
Additional resources
October 29, 2026